ASAP · 1996
No ASAP phase
ASAP started once the decision was made. Evaluation and the business case came before Project Preparation; ValueSAP later wrapped evaluation around the roadmap.
Thirty years of SAP project methodology on one page: how the phases changed and why, which ones decide a project, how long projects take, what they cost, and what changes when you start from a legacy system, from SAP ECC or from an SAP S/4HANA upgrade.
ASAP · 1996effort by phase
1 Project Preparation 12% · 2 Business Blueprint 15% · 3 Realization 46% · 4 Final Preparation 19% · 5 Go-Live and Support 8%
SAP Activate · 2015phases and gates
ASAP bars show the effort share of an early ASAP project plan. Activate shows the six phases and where the gates sit, not effort.
An SAP implementation roadmap is the step-by-step plan SAP publishes for running a project: phases, deliverables, tasks, templates and the checks at the end of each phase. It is the shared language of the customer, the integrator and SAP.
Since 1996 there have been two great ones. AcceleratedSAP (ASAP) took SAP R/3 projects through five sequential phases and a signed Business Blueprint. SAP Activate, launched in 2015 with SAP S/4HANA, starts from a working system with SAP Best Practices, checks it with the business in fit-to-standard workshops and builds only the gaps, in sprints.
Activate is not one plan but a family: SAP publishes a roadmap per product and situation, such as a new implementation, a system conversion, an upgrade or RISE with SAP, in the Roadmap Viewer. Since 2024 the RISE with SAP Methodology adds clean core checks to it for private cloud projects.
years of SAP roadmaps: ASAP arrived for R/3 in 1996, SAP Activate replaced it in 2015, and the RISE with SAP Methodology added clean core checks in 2024.
months to go-live on average: system conversions against new implementations, in ASUG’s 2026 research with 194 members.
more time than planned: SAP S/4HANA projects grew from 15 to 20 months on average in a 2025 Horváth study, and 60% overran budget and deadline.
more likely to meet objectives with excellent change management than with poor, in Prosci’s research with more than 2,600 practitioners.
Evolution
Each method answered what hurt in the one before. Pick a step to see what it brought, which tools came with it and why it gave way.
Step 1 · SAP R/3, up to release 3.1
SAP’s first implementation method came with R/3 itself: a procedure model tied to the Implementation Guide (IMG) and the R/3 Reference Model of business processes. It suited large organisations bringing R/3 in stage by stage, and it was used until release 3.1.
Did you know? In late 1996 the trade press warned that SAP could lose momentum because R/3 took too long to implement. SAP’s answer was AcceleratedSAP, a faster route that delivered R/3 partly preconfigured.
Step 2 · AcceleratedSAP (ASAP), 1996
A roadmap of five phases, from Project Preparation to Go-Live and Support, with templates, questionnaires and checklists for every task. It came as a PC-based package, so a project could start before its R/3 system was even installed, and it aimed at quick, cost-effective projects, often with one big-bang go-live.
Did you know? The Business Blueprint was not written from scratch: it was the output of the Q&A database, built from the answers given for each reference process.
Step 3 · ValueSAP, then SAP Solution Manager
ASAP grew beyond R/3, with roadmaps for CRM, APO, SRM and upgrade projects. It was folded into ValueSAP, which added evaluation and continuous improvement around the implementation, and then into SAP Solution Manager, where the blueprint, configuration, documents and tests of a project lived in one system.
Did you know? SAP Note 576877 described how to move a project’s ASAP content into Solution Manager, which carried the ASAP Implementation Roadmap forward.
Step 4 · ASAP 7 Agile Business Add-on, then ASAP 8 (2012)
SAP published an Agile Business Add-on for ASAP 7, based on Scrum: a product backlog, a baseline build and iterative sprints mapped onto the classic phases. ASAP 8, presented in 2012, put agile, design thinking and visualization into one framework for projects and services, with project quality gates.
Did you know? ASAP 8 was the last version. When SAP Activate arrived in 2015, SAP stopped enhancing ASAP content and kept it available only for projects already using it.
Step 5 · SAP Launch, for SAP’s public cloud
While ASAP served on-premise and managed cloud projects, SAP’s public cloud products had a lighter method of their own, SAP Launch, built for quick starts on preconfigured cloud systems. A customer with a hybrid landscape had to live with two methods.
Did you know? SAP’s own FAQ in 2015 noted that, with ASAP’s assemble-to-order approach, the two methods had already begun to converge.
Step 6 · SAP Activate, SAPPHIRE NOW 2015
Announced at SAPPHIRE NOW 2015, the year SAP S/4HANA was released, SAP Activate replaced both ASAP and SAP Launch. It joins SAP Best Practices (ready-to-run processes), guided configuration and one methodology for cloud, on-premise and hybrid projects. The blueprint gave way to solution validation on a working system.
Did you know? At launch SAP promoted a shorter life cycle of only four phases: Prepare, Explore, Realize and Deploy. Discover and Run were added around them, which gives today’s six. The SAP Activate project manager certification replaced the ASAP one.
Step 7 · RISE with SAP (2021) and GROW with SAP (2023)
SAP now sells SAP S/4HANA mostly as a subscription: RISE with SAP for the private cloud and GROW with SAP for the public cloud. The tools around Activate changed too: the SAP Best Practices Explorer closed on 30 June 2023, replaced by SAP Signavio Process Navigator, and SAP Cloud ALM took over from SAP Solution Manager.
Did you know? Solution Manager has its own 2027 deadline: its mainstream maintenance ends that year too, the less-talked-about second 2027 date in SAP landscapes.
Step 8 · RISE with SAP Methodology, clean core levels, Joule
An enhanced SAP Activate roadmap for SAP S/4HANA Cloud Private Edition. A clean core success plan in SAP Cloud ALM tracks five dimensions, business processes, extensibility, data, integration and operations, with a quality gate at the end of every phase. In 2025 SAP replaced its three-tier extensibility model with clean core levels A to D.
Did you know? An extension takes the level of its least clean part: an ABAP class that uses two released APIs (level A) and one classic API (level B) counts as level B.
Phases
Every Activate phase has an ancestor in ASAP, except Discover. Pick a phase to compare what each method asks for, and what moved.
ASAP · 1996
ASAP started once the decision was made. Evaluation and the business case came before Project Preparation; ValueSAP later wrapped evaluation around the roadmap.
SAP Activate · 2015
Find the value before the contract: explore the solution in a trial system, build the business case, set a first scope and a transition roadmap.
What moved: The case for the project became part of the method, before anyone signs.
ASAP · 1996
Initial planning: scope, standards, the team and the technical requirements, ending with the project kickoff.
SAP Activate · 2015
Start the project: plan, governance, team onboarding and the first systems. For a conversion, run the Readiness Check and plan the transition.
What moved: A system is available in the first weeks, not after the blueprint.
ASAP · 1996
AS-IS and TO-BE workshops documented how the company wanted to run its business in SAP, captured in the Q&A database and signed off as the Business Blueprint.
SAP Activate · 2015
Fit-to-standard workshops walk the business through SAP Best Practices processes in the system. Only the gaps become delta requirements in a backlog, with design, data migration and test plans built around them.
What moved: The business validates a running system instead of signing a document.
ASAP · 1996
Configuration in two work packages, baseline for the major scope and final for the rest, plus programs, interfaces and conversions, and the final integration test.
SAP Activate · 2015
Build and test in sprints: configuration, extensions and integrations from the backlog, repeated data loads, then integration and user acceptance tests. Cutover and training are prepared here.
What moved: Results every sprint instead of one big reveal before the final test.
ASAP · 1996
Testing, end-user training, system management and cutover, resolving every critical open issue before going live.
SAP Activate · 2015
Get ready and go live: end-user training, production data migration, cutover, the go/no-go decision and hypercare.
What moved: Hypercare is part of the phase, not an afterthought once the project team has left.
ASAP · 1996
Moving from a project-oriented pre-production environment to live operation, with post-go-live support and project closure.
SAP Activate · 2015
Operate and keep improving: adopt new releases and feature packs, add scope or countries, and keep the core clean.
What moved: The roadmap no longer ends at go-live: Run carries on with every release.
ASAP percentages: effort share by phase in an early ASAP project plan example. Real projects varied.
Compared
The same goal, a working SAP system, reached from opposite ends: ASAP from a requirements document, Activate from a running system.
| Topic | ASAP | SAP Activate |
|---|---|---|
| Born | 1996, for SAP R/3 | 2015, with SAP S/4HANA |
| Built for | On-premise projects; SAP Launch covered the public cloud | Cloud, on-premise and hybrid, in one method |
| Phases | Five: Project Preparation, Business Blueprint, Realization, Final Preparation, Go-Live and Support | Six: Discover, Prepare, Explore, Realize, Deploy, Run |
| Design starts from | Requirements on paper: AS-IS and TO-BE workshops before the system | A working system with SAP Best Practices, in fit-to-standard workshops |
| Business first sees SAP | After blueprint sign-off, during Realization | In Explore, or already in a Discover trial |
| Gaps | Built as reports, interfaces, conversions, enhancements and forms, often as modifications | Delta requirements in a backlog; extensions follow clean core levels A to D |
| Build | Baseline, then final configuration, in one pass | Iterative sprints in Realize |
| Quality control | Quality check at the end of each phase | Quality gates; the RISE with SAP Methodology adds clean core gates |
| Main tools | Implementation Assistant, Q&A database, later SAP Solution Manager | Roadmap Viewer, Process Navigator, SAP Cloud ALM, SAP Readiness Check |
| Stance on the standard | Adapt SAP to the business | Adapt the business to the standard wherever it is not a real differentiator |
| Status | Superseded in 2015; no further content after ASAP 8 | Current, and the base of the RISE with SAP Methodology |
Why
ASAP was right for its time. Six things made it the wrong tool for SAP S/4HANA and the cloud.
Months of workshops produced a document before anyone saw the system, and by the time Realization delivered, the business had moved on. Activate replaced blueprint activities with solution validation.
Every gap built as a modification had to be retested, and often redone, at the next upgrade. Clean core keeps extensions apart from the standard so upgrades stay routine.
SAP S/4HANA Cloud Public Edition gets two releases a year. A method built for one go-live followed by years of stability did not fit a system that changes every six months.
With SAP Best Practices preconfigured, a project could begin from working processes and change only what really differs, instead of configuring an empty client.
ASAP served on-premise and SAP Launch the cloud. Customers running both needed one approach, one vocabulary and one set of phases.
Sprints show working results every few weeks, so a wrong turn surfaces in Realize rather than in the final integration test.
Activate is a hybrid. Sprints run inside Realize, but the programme around them, with phases, quality gates and a go/no-go decision, is still sequential. Gates work only when they are treated as real controls rather than checkboxes; then they stop problems before they compound.
Scope
In ASAP the scope lived in the Business Process Master List. In Activate it is a set of scope items, each a ready-made business process, plus the delta requirements found in Explore. These are the places to look.
Scope items with process flows, descriptions and test scripts, by product and country. It replaced the SAP Best Practices Explorer, which closed on 30 June 2023.
J58J59J60BD9J45
The Activate roadmaps themselves, in SAP for Me: phases, deliverables, tasks, accelerators and the quality gate checklists, per product and approach.
For a conversion or an upgrade: which simplification items hit your system, add-on compatibility, custom code impact and sizing.
Every functional and technical change between SAP ERP and SAP S/4HANA, and between SAP S/4HANA releases, searchable online.
All new and changed features of a release: the list to read when you plan which delta to adopt in an upgrade.
Where the scope becomes work: requirements, tasks, tests and deployments, and for RISE with SAP the clean core success plan.
Risk
Every phase can sink a project, but risk is not spread evenly. Decisions made in Explore and the data and tests of Realize decide most outcomes.
A weak business case or the wrong approach, such as conversion when the processes need a redesign, is expensive to undo later.
Governance, the team and the partner are set here. Business experts who are only part-time on paper are the most common hidden gap.
Often called the most critical and most underestimated phase. Every gap accepted here becomes build, test and upgrade effort for years; every decision deferred comes back in Realize.
Data migration cycles, custom code and integration tests. Data and custom code are the factors respondents name most when projects run long.
Cutover rehearsals, the go/no-go and hypercare. A cutover that was never rehearsed end to end is a cutover that was never planned.
Adoption after go-live and the first release upgrade. Benefits are lost quietly here, through workarounds and spreadsheets.
People
SAP projects rarely fail on configuration. They fail on scope, decisions and people, which is exactly what these two roles own.
Owns scope, time and money
Watch for: 42% of the projects that missed their go-live date named scope creep as a cause, in ASUG’s 2026 research.
Owns adoption
Watch for: training is one part of change management, not all of it. SAP Activate has change management tasks in every phase, from Discover to Run.
With excellent change management a project is also nearly five times more likely to be on or ahead of schedule, and about one and a half times more likely to stay on or under budget.
Duration
Most independent studies land between 15 and 20 months to go-live. SAP’s own early numbers are shorter; surveys of finished projects, longer. ASUG’s 2024 survey found projects from four months to six years.
Scale: 0 to 24 months. SAP’s 2018 figures cover 1,145 early SAP S/4HANA customers and come from SAP itself.
New implementations averaged 20.2 months, system conversions 15.8 (ASUG 2026). Selective data transition sits in between, depending on how much is redesigned.
Public cloud is new implementation only and the fastest, because the standard is fixed. Private cloud and on-premise allow conversions and deeper extension.
Finance-only projects averaged 7 months in SAP’s 2018 data, typical full-suite projects 11 and the most complex 18.
Each country brings its own law, e-invoicing and statutory reports. Multi-country programmes usually build a global template, then roll out in waves.
49% named custom code to replace or re-engineer among the biggest factors (SAPinsider 2025).
56% named the complexity of the data landscape and 44% data harmonization and cleansing.
Every interface to a system that stays needs design, build and end-to-end testing, often with another vendor’s team.
Business changes (55%) and scope creep (42%) were the causes named most by projects that missed their dates. Fast decisions and available key users shorten projects more than any tool.
Planning aid
A rough planning aid built on the survey averages above. Choose what describes your project and see the range, the phase split and where your go-live would land.
The estimate shown is for a system conversion of the core suite in one country, with some custom code and average data quality. Turn on JavaScript to try your own project.
Estimated duration to go-live
16 months
Plan for 14 to 21 months.
Illustrative phase split
Start in and go live around .
It starts from ASUG’s 2026 averages: 15.8 months for a conversion and 20.2 for a new implementation, with selective data transition assumed at 18. Rule-of-thumb factors follow: public cloud ×0.6; finance only ×0.6, full suite ×1.3; 2–5 countries ×1.15, 6–15 ×1.35, more than 15 ×1.6; a high-complexity localization +2 months; little custom code ×0.9, a lot ×1.2; clean data ×0.95, poor ×1.15. The range runs from 15% below to 30% above, because projects took 30% longer than planned on average in Horváth’s 2025 study. The phase split is a typical planning ratio. A planning aid, not a quote.
Localization
SAP ships country versions with each country’s legal requirements: SAP lists SAP ECC in 65 countries and SAP S/4HANA Cloud Private Edition in 63, both in 39 languages, and the public edition shipped 60 country versions in release 2608. Even with a country version, the effort varies a lot. Pick a country.
In the plan: Plan a dedicated tax and electronic-document workstream, and test every combination of state, operation and material that the business uses.
In the plan: The stamping provider is part of the integration scope, with its own tests and contract.
In the plan: Provincial tax rules change often: keep the tax team close to the project after go-live, not only during it.
In the plan: Portal connectivity and its error handling belong in the integration tests.
In the plan: Plan the tax interface early, together with local partners.
In the plan: Treat SDI rejections and notifications as a process, not just an interface.
In the plan: KSeF turns every invoice into a real-time government exchange: test volumes and outages.
In the plan: Archiving and audit access decisions belong in the design, not after go-live.
In the plan: The tax engine is a project of its own inside the project.
In the plan: Lower legal effort lets the project focus on process and data.
The consumption tax reform runs for eight years. An SAP project in Brazil today builds for the old taxes and the new ones side by side.
Cost
SAP publishes no price list and every deal is negotiated, so read every figure here as an indicative market range, not a quote. Two bills matter: what SAP charges for the software, and what the project costs to deliver.
A one-off licence fee, then annual maintenance: SAP Enterprise Support runs at about 22% of the licence value per year.
2028 to 2030, for two percentage points on top of the maintenance basis, for systems on enhancement package 6 or higher.
One subscription for software, infrastructure and technical operations, usually over several years, priced in full use equivalents (FUE): one advanced user is one FUE, five core users one FUE, thirty self-service users one FUE.
The public edition as a multi-year subscription, also priced in FUEs.
A subscription, not a maintenance extension. Customers committed to private edition by the end of 2025 switch on equivalent terms; 2026 sign-ups face a 20% uplift.
| Company | Users | Year 1 | Year 2 on, per year | Timeline |
|---|---|---|---|---|
| Mid-market, one entity | 20–100 | £200K–£600K | £65K–£160K | 6–12 months |
| Mid-market, several entities | 100–500 | £400K–£1.6M | £160K–£500K | 9–18 months |
| Upper mid-market | 500–2,000 | £1.6M–£6.5M | £500K–£1.6M | 12–24 months |
| Large enterprise | 2,000–10,000+ | £4M–£40M+ | £1.6M–£8M+ | 18–36+ months |
Typical SAP S/4HANA costs in the UK market, ERP Research, 2026.
of annual revenue spent on an ERP project, on average, by Panorama’s clients (2017).
implementation for 500 users with a moderately complex ECC landscape; $15–40M for large global enterprises (Redress Compliance).
Usually the largest single cost. UK day rates run £1,200–2,000 at the Big Four and £1,000–1,800 at global integrators.
Industry estimates add 15–25% to implementation cost for heavily customized ECC systems, and it tends to surface mid-project.
The most underestimated line. Cleansing that starts in Prepare costs less than cleansing during mock loads.
Integration, user acceptance and regression tests. Automation costs more once and pays back at every upgrade.
The cheapest insurance on the list, judging by Prosci’s numbers, and the first line cut when budgets tighten.
Horváth found 60% of SAP S/4HANA projects over budget and deadline. A project without a reserve has simply not met its surprises yet.
The country matters here too: day rates differ widely between markets, and nearshore or offshore delivery lowers the rate, not the effort of the work that must happen on site.
ECC and S/4HANA
Nobody starts a new SAP ECC project now: mainstream maintenance of SAP ERP 6.0 ends on 31 December 2027. But most SAP S/4HANA projects start from an ECC system, so the differences decide the work.
| Topic | SAP ECC implementation | SAP S/4HANA implementation |
|---|---|---|
| Database | Any supported database: Oracle, SQL Server, IBM Db2, SAP MaxDB, SAP ASE or SAP HANA | SAP HANA only |
| Method | ASAP, with a Business Blueprint | SAP Activate, with fit-to-standard |
| Starting point | An empty client configured through the IMG | SAP Best Practices content: working processes to validate |
| Accounting | Classic or new G/L, with controlling, assets and material ledger in their own tables | The Universal Journal: one line item table, ACDOCA |
| Customers and suppliers | Separate customer and vendor masters | Business Partner, mandatory, with customer–vendor integration |
| Inventory valuation | Material ledger optional | Material ledger mandatory |
| Asset accounting | Classic asset accounting | New asset accounting, mandatory |
| Credit management | FI-AR credit management | SAP Credit Management |
| Profitability | Costing-based CO-PA common | Margin analysis recommended; costing-based still available |
| User experience | SAP GUI | SAP Fiori, with SAP GUI still available on-premise and in private cloud |
| Reporting | ABAP reports and a separate SAP BW | Embedded analytics on CDS views |
| Planning and output | Classic MRP; NAST-based output | MRP Live; SAP S/4HANA output control |
| Extensions | User exits, BAdIs and modifications | Clean core levels A to D, ABAP Cloud and SAP BTP |
| Releases | Enhancement packages on SAP ERP 6.0 | A release every two years since 2023, feature packs every six months; public cloud twice a year |
| Support horizon | Mainstream to 2027, extended to 2030 | Seven years per release; SAP’s commitment runs to 2040 |
A new system with processes redesigned on SAP Best Practices. Usually only master data, open items and balances move.
Best when processes need a redesign, the ECC is heavily customized or you come from a non-SAP system. The only road to the public cloud.
Watch the longest average, 20.2 months, and the most change for users. History stays in the old system or an archive.
Converts the existing system, with its configuration, custom code and history, using the Software Update Manager.
Best when the processes still fit and history must stay online. Chosen by 47% in ASUG’s 2026 research, averaging 15.8 months.
Watch old customizing and custom code travel too. Clean up before converting, and plan the improvements after.
A reshaped new system loaded with chosen data from the old one, by company code, year or object, usually with specialist tools.
Best when you want to keep some history and redesign some processes, or merge and split systems along the way.
Watch dependence on tools and partners, and more complex reconciliation and testing.
Upgrades
Once you are live, the roadmap carries on in Run: every release has a fixed maintenance window, so upgrades become part of the plan rather than a surprise.
Bars run to the end of the year shown. The 2027 release follows SAP’s announced two-year cycle. The highlighted column is 2026.
The delta is what fit-to-standard did not cover: the delta requirements in the Explore backlog, designed and built in Realize. Only the gaps get a design document.
The delta is only what changed between your release and the target: the simplification items that hit your system, the custom code to adapt, and the new features you choose to adopt.
Technical upgrade: the new release with as little business change as possible. Functional upgrade: the technical upgrade plus new features and processes, which takes longer because it carries scope.
SPDD for the dictionary, SPAU for repository objectssimplification items were relevant in a Readiness Check for an SAP S/4HANA upgrade published by a New York State agency in 2025; 7 more needed a manual check.
for one upgrade case shown at an ASUG chapter event, with four upgrade cycles: sandbox, development, quality and production.
is the longest a RISE with SAP private edition customer can go without an upgrade and stay in mainstream maintenance. SAP accepts one upgrade request a year.
is what an SAP ERP 6.0 system needs for extended maintenance to 2030. The 2033 option also requires moving to SAP ERP, private edition, by the end of 2030.
Starting point
A company new to SAP, one running ECC for twenty years and one already on SAP S/4HANA face very different problems. Pick your starting point.
Everything is new: the system, the data model and often the way of working.
You know SAP, which helps, and you carry years of decisions, which does not.
The move is done. Now the roadmap is about staying current and staying clean.
Quiz
Seven things people say about SAP roadmaps and deadlines. Decide, then see the answer.
The plan SAP publishes for running an SAP project: its phases, deliverables, tasks, accelerators and quality checks. Today these are the SAP Activate roadmaps in the Roadmap Viewer, with one roadmap per product and situation, such as a new implementation, a system conversion, an upgrade or RISE with SAP.
Six: Discover, Prepare, Explore, Realize, Deploy and Run. Prepare to Deploy are the four core delivery phases, with quality gates between them; Discover comes before the project and Run after go-live.
Five: Project Preparation, Business Blueprint, Realization, Final Preparation, and Go-Live and Support, each ending with a quality check. The Business Blueprint was the signed description of how the company would run its business in SAP.
ASAP designed on paper first and built in one pass; Activate starts from SAP Best Practices on a working system, validates it in fit-to-standard workshops and builds only the gaps in sprints. ASAP served on-premise projects; Activate covers cloud, on-premise and hybrid.
A formal checkpoint at a phase transition, where the key deliverables of the phase are reviewed and signed off before the next phase starts. The RISE with SAP Methodology adds clean core checks to a gate at the end of every phase.
About 15 to 20 months on average. ASUG’s 2026 research found 15.8 months for system conversions and 20.2 for new implementations, with an overall average of about 1.4 years, and its 2024 survey found projects from four months to six years.
There is no list price. UK market ranges for 2026 run from about £200,000 in the first year for a small single-entity company to tens of millions of pounds for large enterprises, with software, integrator, data, testing and change management as the main lines.
Greenfield, a new implementation, suits companies that want to redesign processes or come from a non-SAP system. Brownfield, a system conversion, suits companies whose processes still fit and who want to keep history. Selective data transition sits between them.
Mainstream maintenance for SAP ERP 6.0 ends on 31 December 2027. Extended maintenance runs from 2028 to 2030 for an extra two percentage points. After that, the SAP ERP, private edition, transition option covers 2031 to 2033 for customers who move to that private cloud edition by the end of 2030.
Checked in October 2026. Costs are indicative market ranges: SAP publishes no price list.