The SAP implementation roadmap: from ASAP to SAP Activate

Thirty years of SAP project methodology on one page: how the phases changed and why, which ones decide a project, how long projects take, what they cost, and what changes when you start from a legacy system, from SAP ECC or from an SAP S/4HANA upgrade.

  • ASAP
  • SAP Activate
  • Fit-to-standard
  • Quality gates
  • RISE with SAP
  • Clean core
  • Timeline and cost

What is an SAP implementation roadmap?

An SAP implementation roadmap is the step-by-step plan SAP publishes for running a project: phases, deliverables, tasks, templates and the checks at the end of each phase. It is the shared language of the customer, the integrator and SAP.

Since 1996 there have been two great ones. AcceleratedSAP (ASAP) took SAP R/3 projects through five sequential phases and a signed Business Blueprint. SAP Activate, launched in 2015 with SAP S/4HANA, starts from a working system with SAP Best Practices, checks it with the business in fit-to-standard workshops and builds only the gaps, in sprints.

Activate is not one plan but a family: SAP publishes a roadmap per product and situation, such as a new implementation, a system conversion, an upgrade or RISE with SAP, in the Roadmap Viewer. Since 2024 the RISE with SAP Methodology adds clean core checks to it for private cloud projects.

SAP projects in four numbers

  • 30

    years of SAP roadmaps: ASAP arrived for R/3 in 1996, SAP Activate replaced it in 2015, and the RISE with SAP Methodology added clean core checks in 2024.

  • 15.8 · 20.2

    months to go-live on average: system conversions against new implementations, in ASUG’s 2026 research with 194 members.

  • +30%

    more time than planned: SAP S/4HANA projects grew from 15 to 20 months on average in a 2025 Horváth study, and 60% overran budget and deadline.

  • 7×

    more likely to meet objectives with excellent change management than with poor, in Prosci’s research with more than 2,600 practitioners.

Evolution

Thirty years of SAP roadmaps in eight steps

Each method answered what hurt in the one before. Pick a step to see what it brought, which tools came with it and why it gave way.

Step

Step 1 · SAP R/3, up to release 3.1

The R/3 Procedure Model

SAP’s first implementation method came with R/3 itself: a procedure model tied to the Implementation Guide (IMG) and the R/3 Reference Model of business processes. It suited large organisations bringing R/3 in stage by stage, and it was used until release 3.1.

Tools and names

  • IMG
  • R/3 Reference Model
  • Procedure Model

What it brought

  • One way to configure: the IMG, step by step
  • Reference processes to hold the business against
  • A model for staged introductions in large companies

Why it gave way

  • Long projects that leaned on large consultant teams
  • Little packaged help for project management, training and change
  • Too slow for medium-sized companies that wanted one go-live

Did you know? In late 1996 the trade press warned that SAP could lose momentum because R/3 took too long to implement. SAP’s answer was AcceleratedSAP, a faster route that delivered R/3 partly preconfigured.

Step 2 · AcceleratedSAP (ASAP), 1996

AcceleratedSAP (ASAP)

A roadmap of five phases, from Project Preparation to Go-Live and Support, with templates, questionnaires and checklists for every task. It came as a PC-based package, so a project could start before its R/3 system was even installed, and it aimed at quick, cost-effective projects, often with one big-bang go-live.

Tools and names

  • Implementation Assistant
  • Q&A database
  • Business Process Master List
  • Business Process Procedures
  • Issues database

What it brought

  • A standard roadmap: phases, work packages, activities and tasks
  • Requirements captured as answers in the Q&A database, per reference process
  • A quality check at the end of every phase

What still hurt

  • The Business Blueprint took months of workshops before anyone saw a system
  • Configuration came in one pass: baseline, then final
  • Gaps became custom developments, often modifications that made later upgrades expensive

Did you know? The Business Blueprint was not written from scratch: it was the output of the Q&A database, built from the answers given for each reference process.

Step 3 · ValueSAP, then SAP Solution Manager

ValueSAP and SAP Solution Manager

ASAP grew beyond R/3, with roadmaps for CRM, APO, SRM and upgrade projects. It was folded into ValueSAP, which added evaluation and continuous improvement around the implementation, and then into SAP Solution Manager, where the blueprint, configuration, documents and tests of a project lived in one system.

Tools and names

  • ValueSAP
  • SAP Solution Manager
  • Business Process Repository
  • ASAP Roadmap for Upgrade

What it brought

  • Project documentation stored in a system, not on file shares
  • Transactions launched from the blueprint structure during Realization
  • Roadmaps for other SAP products and for upgrades

What still hurt

  • The method itself stayed the same: blueprint first, build later
  • Solution Manager was one more system to install, run and patch

Did you know? SAP Note 576877 described how to move a project’s ASAP content into Solution Manager, which carried the ASAP Implementation Roadmap forward.

Step 4 · ASAP 7 Agile Business Add-on, then ASAP 8 (2012)

ASAP goes agile

SAP published an Agile Business Add-on for ASAP 7, based on Scrum: a product backlog, a baseline build and iterative sprints mapped onto the classic phases. ASAP 8, presented in 2012, put agile, design thinking and visualization into one framework for projects and services, with project quality gates.

Tools and names

  • Agile Business Add-on
  • ASAP 8
  • Rapid-deployment solutions
  • Quality gates

What it brought

  • Sprints and a backlog instead of one long build
  • Closer, continuous work between IT and the business
  • Preconfigured rapid-deployment packages: some projects skipped the blueprint

What still hurt

  • Still a method for on-premise systems; the cloud had its own
  • The blueprint remained the default in standard ASAP projects

Did you know? ASAP 8 was the last version. When SAP Activate arrived in 2015, SAP stopped enhancing ASAP content and kept it available only for projects already using it.

Step 5 · SAP Launch, for SAP’s public cloud

SAP Launch

While ASAP served on-premise and managed cloud projects, SAP’s public cloud products had a lighter method of their own, SAP Launch, built for quick starts on preconfigured cloud systems. A customer with a hybrid landscape had to live with two methods.

Tools and names

  • SAP Launch
  • Public cloud solutions

What it brought

  • Short projects on systems that already worked
  • Configuration rather than development

What still hurt

  • It covered the initial setup and launch, not a full transformation
  • A different vocabulary and phases from ASAP, inside the same company

Did you know? SAP’s own FAQ in 2015 noted that, with ASAP’s assemble-to-order approach, the two methods had already begun to converge.

Step 6 · SAP Activate, SAPPHIRE NOW 2015

SAP Activate

Announced at SAPPHIRE NOW 2015, the year SAP S/4HANA was released, SAP Activate replaced both ASAP and SAP Launch. It joins SAP Best Practices (ready-to-run processes), guided configuration and one methodology for cloud, on-premise and hybrid projects. The blueprint gave way to solution validation on a working system.

Tools and names

  • SAP Best Practices
  • Guided configuration
  • Roadmap Viewer
  • SAP Activate certification

What it brought

  • Start from a working system, not from a requirements document
  • Fit-to-standard workshops: show the standard, record only the gaps
  • Agile build in sprints, with quality gates between phases

What to watch

  • Sprints inside, but phases, gates and go/no-go are still sequential
  • Fit-to-standard needs a business that is willing to change its processes

Did you know? At launch SAP promoted a shorter life cycle of only four phases: Prepare, Explore, Realize and Deploy. Discover and Run were added around them, which gives today’s six. The SAP Activate project manager certification replaced the ASAP one.

Step 7 · RISE with SAP (2021) and GROW with SAP (2023)

RISE with SAP and a new toolset

SAP now sells SAP S/4HANA mostly as a subscription: RISE with SAP for the private cloud and GROW with SAP for the public cloud. The tools around Activate changed too: the SAP Best Practices Explorer closed on 30 June 2023, replaced by SAP Signavio Process Navigator, and SAP Cloud ALM took over from SAP Solution Manager.

Tools and names

  • RISE with SAP
  • GROW with SAP
  • SAP Signavio Process Navigator
  • SAP Cloud ALM
  • SAP Readiness Check

What it brought

  • Software, infrastructure and technical operations in one contract
  • Scope items, process flows and test scripts in Process Navigator
  • Project tasks, tests and deployments in Cloud ALM

What to watch

  • Cloud ALM does not replace every Solution Manager scenario one to one
  • Release upgrades became a recurring duty, not a rare project

Did you know? Solution Manager has its own 2027 deadline: its mainstream maintenance ends that year too, the less-talked-about second 2027 date in SAP landscapes.

Step 8 · RISE with SAP Methodology, clean core levels, Joule

RISE with SAP Methodology

An enhanced SAP Activate roadmap for SAP S/4HANA Cloud Private Edition. A clean core success plan in SAP Cloud ALM tracks five dimensions, business processes, extensibility, data, integration and operations, with a quality gate at the end of every phase. In 2025 SAP replaced its three-tier extensibility model with clean core levels A to D.

Tools and names

  • Clean core success plan
  • Clean core levels A–D
  • SAP Cloud ALM
  • Joule for consultants

What it brought

  • Clean core measured, not just recommended
  • Five onboarding calls with an SAP advisor during Prepare
  • AI help for project teams through Joule

What to watch

  • Level C and D extensions still slow every upgrade
  • More governance for customers and partners to staff

Did you know? An extension takes the level of its least clean part: an ABAP class that uses two released APIs (level A) and one classic API (level B) counts as level B.

Phases

The phases side by side

Every Activate phase has an ancestor in ASAP, except Discover. Pick a phase to compare what each method asks for, and what moved.

Phase

ASAP · 1996

No ASAP phase

ASAP started once the decision was made. Evaluation and the business case came before Project Preparation; ValueSAP later wrapped evaluation around the roadmap.

SAP Activate · 2015

Discover

No quality gate

Find the value before the contract: explore the solution in a trial system, build the business case, set a first scope and a transition roadmap.

Key deliverables

  • Value discovery and business case
  • Trial system and solution demos
  • High-level scope
  • Transition roadmap

What moved: The case for the project became part of the method, before anyone signs.

ASAP · 1996

Project Preparation

12%

Initial planning: scope, standards, the team and the technical requirements, ending with the project kickoff.

Key deliverables

  • Project charter and scope document
  • Project plan, standards and procedures
  • Team formation and kickoff
  • Technical requirements
  • Quality check

SAP Activate · 2015

Prepare

Quality gate at the end

Start the project: plan, governance, team onboarding and the first systems. For a conversion, run the Readiness Check and plan the transition.

Key deliverables

  • Project charter, plan and governance
  • Team onboarding and enablement
  • Starter or sandbox system
  • Readiness Check and transition plan, for conversions
  • Change impact baseline and stakeholder map

What moved: A system is available in the first weeks, not after the blueprint.

ASAP · 1996

Business Blueprint

15%

AS-IS and TO-BE workshops documented how the company wanted to run its business in SAP, captured in the Q&A database and signed off as the Business Blueprint.

Key deliverables

  • Requirements workshops
  • Business Process Master List
  • Organizational structure
  • Business Blueprint, signed off
  • Development system set up

SAP Activate · 2015

Explore

Quality gate at the end

Fit-to-standard workshops walk the business through SAP Best Practices processes in the system. Only the gaps become delta requirements in a backlog, with design, data migration and test plans built around them.

Key deliverables

  • Fit-to-standard workshops per scope item
  • Delta requirements backlog
  • Solution and extension design
  • Data migration design and plan
  • Test strategy; custom code analysis for conversions

What moved: The business validates a running system instead of signing a document.

ASAP · 1996

Realization

46%

Configuration in two work packages, baseline for the major scope and final for the rest, plus programs, interfaces and conversions, and the final integration test.

Key deliverables

  • Baseline configuration and confirmation
  • Final configuration and confirmation
  • Reports, interfaces, conversions, enhancements and forms
  • Unit and final integration tests
  • End-user documentation

SAP Activate · 2015

Realize

Quality gate at the end

Build and test in sprints: configuration, extensions and integrations from the backlog, repeated data loads, then integration and user acceptance tests. Cutover and training are prepared here.

Key deliverables

  • Sprint builds of configuration, extensions and interfaces
  • Mock data loads
  • Integration and user acceptance tests
  • Cutover plan
  • Training material

What moved: Results every sprint instead of one big reveal before the final test.

ASAP · 1996

Final Preparation

19%

Testing, end-user training, system management and cutover, resolving every critical open issue before going live.

Key deliverables

  • Stress and volume tests
  • End-user training
  • Cutover plan and data loads
  • Go-live decision

SAP Activate · 2015

Deploy

Quality gate at the end

Get ready and go live: end-user training, production data migration, cutover, the go/no-go decision and hypercare.

Key deliverables

  • End-user training
  • Production data migration
  • Cutover and go/no-go
  • Go-live
  • Hypercare and handover to support

What moved: Hypercare is part of the phase, not an afterthought once the project team has left.

ASAP · 1996

Go-Live and Support

8%

Moving from a project-oriented pre-production environment to live operation, with post-go-live support and project closure.

Key deliverables

  • Production support
  • Handover and project closure

SAP Activate · 2015

Run

Ongoing

Operate and keep improving: adopt new releases and feature packs, add scope or countries, and keep the core clean.

Key deliverables

  • Operations and support
  • Release upgrades and feature adoption
  • New scope items and countries
  • Continuous improvement

What moved: The roadmap no longer ends at go-live: Run carries on with every release.

ASAP percentages: effort share by phase in an early ASAP project plan example. Real projects varied.

Compared

ASAP vs SAP Activate

The same goal, a working SAP system, reached from opposite ends: ASAP from a requirements document, Activate from a running system.

ASAP and SAP Activate compared
TopicASAPSAP Activate
Born1996, for SAP R/32015, with SAP S/4HANA
Built forOn-premise projects; SAP Launch covered the public cloudCloud, on-premise and hybrid, in one method
PhasesFive: Project Preparation, Business Blueprint, Realization, Final Preparation, Go-Live and SupportSix: Discover, Prepare, Explore, Realize, Deploy, Run
Design starts fromRequirements on paper: AS-IS and TO-BE workshops before the systemA working system with SAP Best Practices, in fit-to-standard workshops
Business first sees SAPAfter blueprint sign-off, during RealizationIn Explore, or already in a Discover trial
GapsBuilt as reports, interfaces, conversions, enhancements and forms, often as modificationsDelta requirements in a backlog; extensions follow clean core levels A to D
BuildBaseline, then final configuration, in one passIterative sprints in Realize
Quality controlQuality check at the end of each phaseQuality gates; the RISE with SAP Methodology adds clean core gates
Main toolsImplementation Assistant, Q&A database, later SAP Solution ManagerRoadmap Viewer, Process Navigator, SAP Cloud ALM, SAP Readiness Check
Stance on the standardAdapt SAP to the businessAdapt the business to the standard wherever it is not a real differentiator
StatusSuperseded in 2015; no further content after ASAP 8Current, and the base of the RISE with SAP Methodology

Why

Why SAP had to change the method

ASAP was right for its time. Six things made it the wrong tool for SAP S/4HANA and the cloud.

  1. 01

    The blueprint went stale

    Months of workshops produced a document before anyone saw the system, and by the time Realization delivered, the business had moved on. Activate replaced blueprint activities with solution validation.

  2. 02

    Custom code became debt

    Every gap built as a modification had to be retested, and often redone, at the next upgrade. Clean core keeps extensions apart from the standard so upgrades stay routine.

  3. 03

    The cloud does not wait

    SAP S/4HANA Cloud Public Edition gets two releases a year. A method built for one go-live followed by years of stability did not fit a system that changes every six months.

  4. 04

    The standard became a starting point

    With SAP Best Practices preconfigured, a project could begin from working processes and change only what really differs, instead of configuring an empty client.

  5. 05

    One method for every deployment

    ASAP served on-premise and SAP Launch the cloud. Customers running both needed one approach, one vocabulary and one set of phases.

  6. 06

    Earlier feedback, earlier value

    Sprints show working results every few weeks, so a wrong turn surfaces in Realize rather than in the final integration test.

Agile inside, sequential outside

Activate is a hybrid. Sprints run inside Realize, but the programme around them, with phases, quality gates and a go/no-go decision, is still sequential. Gates work only when they are treated as real controls rather than checkboxes; then they stop problems before they compound.

Scope

How to see and set the scope

In ASAP the scope lived in the Business Process Master List. In Activate it is a set of scope items, each a ready-made business process, plus the delta requirements found in Explore. These are the places to look.

  • SAP Signavio Process Navigator

    Scope items with process flows, descriptions and test scripts, by product and country. It replaced the SAP Best Practices Explorer, which closed on 30 June 2023.

    J58J59J60BD9J45

  • Roadmap Viewer

    The Activate roadmaps themselves, in SAP for Me: phases, deliverables, tasks, accelerators and the quality gate checklists, per product and approach.

  • SAP Readiness Check

    For a conversion or an upgrade: which simplification items hit your system, add-on compatibility, custom code impact and sizing.

  • Simplification Item Catalog

    Every functional and technical change between SAP ERP and SAP S/4HANA, and between SAP S/4HANA releases, searchable online.

  • What’s New Viewer

    All new and changed features of a release: the list to read when you plan which delta to adopt in an upgrade.

  • SAP Cloud ALM

    Where the scope becomes work: requirements, tasks, tests and deployments, and for RISE with SAP the clean core success plan.

Risk

Which phases are most critical

Every phase can sink a project, but risk is not spread evenly. Decisions made in Explore and the data and tests of Realize decide most outcomes.

  • Discover

    Medium

    A weak business case or the wrong approach, such as conversion when the processes need a redesign, is expensive to undo later.

  • Prepare

    High

    Governance, the team and the partner are set here. Business experts who are only part-time on paper are the most common hidden gap.

  • Explore

    Very high

    Often called the most critical and most underestimated phase. Every gap accepted here becomes build, test and upgrade effort for years; every decision deferred comes back in Realize.

  • Realize

    Very high

    Data migration cycles, custom code and integration tests. Data and custom code are the factors respondents name most when projects run long.

  • Deploy

    High

    Cutover rehearsals, the go/no-go and hypercare. A cutover that was never rehearsed end to end is a cutover that was never planned.

  • Run

    Medium

    Adoption after go-live and the first release upgrade. Benefits are lost quietly here, through workarounds and spreadsheets.

Why projects missed their datesRespondents who missed their go-live, ASUG 2026
  1. Business changes55%
  2. Unexpected complexity45%
  3. Scope creep42%
What stretches the timelineBiggest factors named, SAPinsider 2025
  1. Complexity of the data landscape56%
  2. Custom code to replace or re-engineer49%
  3. Data harmonization and cleansing44%

People

The project manager and the change manager

SAP projects rarely fail on configuration. They fail on scope, decisions and people, which is exactly what these two roles own.

Owns scope, time and money

Project manager

  • Holds the scope: every change request priced in time and money before anyone accepts it
  • Runs governance: steering committee, plan, risks, issues and the quality gates
  • Keeps business experts available: fit-to-standard and testing need the people who run the processes
  • Coordinates the customer, the integrator, SAP and every third party
  • Brings facts to the go/no-go: test results, data reconciliation, the cutover rehearsal

Watch for: 42% of the projects that missed their go-live date named scope creep as a cause, in ASUG’s 2026 research.

Owns adoption

Change manager

  • Maps who is affected: the roles, transactions and reports that change, and how much
  • Builds sponsorship: leaders who explain why the change matters, in their own words
  • Plans communication and role-based training, with key users as multipliers
  • Measures readiness before go-live and adoption after it
  • Handles resistance early, before it shows up in testing or as workarounds

Watch for: training is one part of change management, not all of it. SAP Activate has change management tasks in every phase, from Discover to Run.

Change management and resultsProjects that met or exceeded objectives, by quality of change management (Prosci)
  1. Excellent88%
  2. Good73%
  3. Fair39%
  4. Poor13%

With excellent change management a project is also nearly five times more likely to be on or ahead of schedule, and about one and a half times more likely to stay on or under budget.

Duration

How long an SAP project takes

Most independent studies land between 15 and 20 months to go-live. SAP’s own early numbers are shorter; surveys of finished projects, longer. ASUG’s 2024 survey found projects from four months to six years.

Average duration by study, in monthsOther studiesASUG 2026
  1. SAP 2018 · finance-only projects7
  2. SAP 2018 · typical full-suite projects11
  3. Horváth 2025 · as planned15
  4. ASUG 2026 · system conversion15.8
  5. ASUG 2026 · all projects, about 1.4 years≈17
  6. Panorama 2017 · ERP projects16.9
  7. SAPinsider 2024 · average deployment18
  8. SAP 2018 · complex projects, largest customers18
  9. Horváth 2025 · actual20
  10. ASUG 2026 · new implementation20.2

Scale: 0 to 24 months. SAP’s 2018 figures cover 1,145 early SAP S/4HANA customers and come from SAP itself.

Eight things that set the length

  • Approach

    New implementations averaged 20.2 months, system conversions 15.8 (ASUG 2026). Selective data transition sits in between, depending on how much is redesigned.

  • Deployment

    Public cloud is new implementation only and the fastest, because the standard is fixed. Private cloud and on-premise allow conversions and deeper extension.

  • Scope

    Finance-only projects averaged 7 months in SAP’s 2018 data, typical full-suite projects 11 and the most complex 18.

  • Countries

    Each country brings its own law, e-invoicing and statutory reports. Multi-country programmes usually build a global template, then roll out in waves.

  • Custom code

    49% named custom code to replace or re-engineer among the biggest factors (SAPinsider 2025).

  • Data

    56% named the complexity of the data landscape and 44% data harmonization and cleansing.

  • Integrations

    Every interface to a system that stays needs design, build and end-to-end testing, often with another vendor’s team.

  • Decisions and people

    Business changes (55%) and scope creep (42%) were the causes named most by projects that missed their dates. Fast decisions and available key users shorten projects more than any tool.

Planning aid

Estimate your timeline

A rough planning aid built on the survey averages above. Choose what describes your project and see the range, the phase split and where your go-live would land.

The estimate shown is for a system conversion of the core suite in one country, with some custom code and average data quality. Turn on JavaScript to try your own project.

Estimated duration to go-live

16 months

Plan for 14 to 21 months.

Illustrative phase split

13822
  • Prepare · 1 mo
  • Explore · 3 mo
  • Realize · 8 mo
  • Deploy · 2 mo
  • Hypercare · 2 mo
How the estimate works

It starts from ASUG’s 2026 averages: 15.8 months for a conversion and 20.2 for a new implementation, with selective data transition assumed at 18. Rule-of-thumb factors follow: public cloud ×0.6; finance only ×0.6, full suite ×1.3; 2–5 countries ×1.15, 6–15 ×1.35, more than 15 ×1.6; a high-complexity localization +2 months; little custom code ×0.9, a lot ×1.2; clean data ×0.95, poor ×1.15. The range runs from 15% below to 30% above, because projects took 30% longer than planned on average in Horváth’s 2025 study. The phase split is a typical planning ratio. A planning aid, not a quote.

Localization

Localization: why the country changes the plan

SAP ships country versions with each country’s legal requirements: SAP lists SAP ECC in 65 countries and SAP S/4HANA Cloud Private Edition in 63, both in 39 languages, and the public edition shipped 60 country versions in release 2608. Even with a country version, the effort varies a lot. Pick a country.

Country

Brazil

Localization effort: Very high

What drives the effort

  • Electronic documents authorised by the tax authorities before goods move: NF-e, NFC-e, CT-e and NFS-e
  • SPED digital bookkeeping and tax files: ECD, ECF, EFD ICMS/IPI, EFD Contribuições and EFD-Reinf
  • ICMS rules that change by state, with tax substitution (ST) and the interstate rate difference (DIFAL)
  • Tax reform: IBS and CBS fields mandatory on NF-e, NFC-e and CT-e since 3 August 2026, with old and new taxes side by side until 2033

In the plan: Plan a dedicated tax and electronic-document workstream, and test every combination of state, operation and material that the business uses.

Mexico

Localization effort: High

What drives the effort

  • CFDI 4.0 electronic invoices stamped by an authorised provider (PAC) for the tax authority, SAT
  • Payment complements for invoices paid later, and the Carta Porte complement for goods in transit
  • Electronic accounting: chart of accounts and trial balance sent to SAT

In the plan: The stamping provider is part of the integration scope, with its own tests and contract.

Argentina

Localization effort: High

What drives the effort

  • Electronic invoicing authorised by ARCA, formerly AFIP
  • Withholding and perception regimes that differ by province
  • Inflation adjustment of financial statements

In the plan: Provincial tax rules change often: keep the tax team close to the project after go-live, not only during it.

India

Localization effort: High

What drives the effort

  • GST with e-invoicing: invoices registered on the government portal to obtain an IRN
  • E-way bills for moving goods
  • TDS and TCS withholding

In the plan: Portal connectivity and its error handling belong in the integration tests.

China

Localization effort: High

What drives the effort

  • The Golden Tax system and fapiao invoices, moving to fully digital e-invoices
  • Interfaces to state-controlled tax systems
  • Local language and local hosting questions

In the plan: Plan the tax interface early, together with local partners.

Italy

Localization effort: Medium

What drives the effort

  • All invoices, B2B included, exchanged through the SDI system as FatturaPA XML since 2019
  • A mature country version; most effort sits in the e-invoicing integration

In the plan: Treat SDI rejections and notifications as a process, not just an interface.

Poland

Localization effort: Medium

What drives the effort

  • National e-invoicing system KSeF, mandatory from 2026
  • JPK SAF-T files for the tax authority

In the plan: KSeF turns every invoice into a real-time government exchange: test volumes and outages.

Germany

Localization effort: Medium

What drives the effort

  • GoBD rules for digital bookkeeping and archiving
  • Receiving e-invoices mandatory since 2025; issuing them becomes mandatory in 2027 and 2028

In the plan: Archiving and audit access decisions belong in the design, not after go-live.

United States

Localization effort: Medium

What drives the effort

  • No VAT, but sales and use tax across thousands of jurisdictions, usually calculated by an external tax engine
  • 1099 reporting for suppliers

In the plan: The tax engine is a project of its own inside the project.

United Kingdom

Localization effort: Lower

What drives the effort

  • Making Tax Digital for VAT: digital records and returns sent through software
  • A mature country version

In the plan: Lower legal effort lets the project focus on process and data.

Brazil, 2026 to 2033: two tax systems at once

The consumption tax reform runs for eight years. An SAP project in Brazil today builds for the old taxes and the new ones side by side.

  1. 2026Test year: CBS 0.9% and IBS 0.1% shown on documents; PIS and COFINS still paid
  2. Aug–Oct 2026IBS and CBS fields mandatory: NF-e, NFC-e and CT-e from 3 August, NFS-e from 1 October
  3. 2027CBS charged, PIS and COFINS end, Selective Tax (IS) starts; in 2027–2028 IBS runs at a 0.1% test rate and CBS 0.1 point below its reference rate
  4. 2029–2032ICMS and ISS step down as IBS steps up
  5. 2033ICMS and ISS end: IBS, CBS and IS only

Cost

What an SAP project costs

SAP publishes no price list and every deal is negotiated, so read every figure here as an indicative market range, not a quote. Two bills matter: what SAP charges for the software, and what the project costs to deliver.

What SAP charges

  • On-premise licence

    A one-off licence fee, then annual maintenance: SAP Enterprise Support runs at about 22% of the licence value per year.

  • Extended maintenance for SAP ERP 6.0

    2028 to 2030, for two percentage points on top of the maintenance basis, for systems on enhancement package 6 or higher.

  • RISE with SAP

    One subscription for software, infrastructure and technical operations, usually over several years, priced in full use equivalents (FUE): one advanced user is one FUE, five core users one FUE, thirty self-service users one FUE.

  • GROW with SAP

    The public edition as a multi-year subscription, also priced in FUEs.

  • The 2031–2033 transition option

    A subscription, not a maintenance extension. Customers committed to private edition by the end of 2025 switch on equivalent terms; 2026 sign-ups face a 20% uplift.

What the project costs

Typical SAP S/4HANA costs in the UK market, ERP Research, 2026.
CompanyUsersYear 1Year 2 on, per yearTimeline
Mid-market, one entity20–100£200K–£600K£65K–£160K6–12 months
Mid-market, several entities100–500£400K–£1.6M£160K–£500K9–18 months
Upper mid-market500–2,000£1.6M–£6.5M£500K–£1.6M12–24 months
Large enterprise2,000–10,000+£4M–£40M+£1.6M–£8M+18–36+ months

Typical SAP S/4HANA costs in the UK market, ERP Research, 2026.

  • 3.6%

    of annual revenue spent on an ERP project, on average, by Panorama’s clients (2017).

  • $2.5–5M

    implementation for 500 users with a moderately complex ECC landscape; $15–40M for large global enterprises (Redress Compliance).

Where the project money goes

  • The integrator

    Usually the largest single cost. UK day rates run £1,200–2,000 at the Big Four and £1,000–1,800 at global integrators.

  • Custom code remediation

    Industry estimates add 15–25% to implementation cost for heavily customized ECC systems, and it tends to surface mid-project.

  • Data migration and cleansing

    The most underestimated line. Cleansing that starts in Prepare costs less than cleansing during mock loads.

  • Testing

    Integration, user acceptance and regression tests. Automation costs more once and pays back at every upgrade.

  • Change and training

    The cheapest insurance on the list, judging by Prosci’s numbers, and the first line cut when budgets tighten.

  • Contingency

    Horváth found 60% of SAP S/4HANA projects over budget and deadline. A project without a reserve has simply not met its surprises yet.

The country matters here too: day rates differ widely between markets, and nearshore or offshore delivery lowers the rate, not the effort of the work that must happen on site.

ECC and S/4HANA

Implementing SAP ECC vs SAP S/4HANA

Nobody starts a new SAP ECC project now: mainstream maintenance of SAP ERP 6.0 ends on 31 December 2027. But most SAP S/4HANA projects start from an ECC system, so the differences decide the work.

An SAP ECC implementation and an SAP S/4HANA implementation compared
TopicSAP ECC implementationSAP S/4HANA implementation
DatabaseAny supported database: Oracle, SQL Server, IBM Db2, SAP MaxDB, SAP ASE or SAP HANASAP HANA only
MethodASAP, with a Business BlueprintSAP Activate, with fit-to-standard
Starting pointAn empty client configured through the IMGSAP Best Practices content: working processes to validate
AccountingClassic or new G/L, with controlling, assets and material ledger in their own tablesThe Universal Journal: one line item table, ACDOCA
Customers and suppliersSeparate customer and vendor mastersBusiness Partner, mandatory, with customer–vendor integration
Inventory valuationMaterial ledger optionalMaterial ledger mandatory
Asset accountingClassic asset accountingNew asset accounting, mandatory
Credit managementFI-AR credit managementSAP Credit Management
ProfitabilityCosting-based CO-PA commonMargin analysis recommended; costing-based still available
User experienceSAP GUISAP Fiori, with SAP GUI still available on-premise and in private cloud
ReportingABAP reports and a separate SAP BWEmbedded analytics on CDS views
Planning and outputClassic MRP; NAST-based outputMRP Live; SAP S/4HANA output control
ExtensionsUser exits, BAdIs and modificationsClean core levels A to D, ABAP Cloud and SAP BTP
ReleasesEnhancement packages on SAP ERP 6.0A release every two years since 2023, feature packs every six months; public cloud twice a year
Support horizonMainstream to 2027, extended to 2030Seven years per release; SAP’s commitment runs to 2040

Three roads from SAP ECC to SAP S/4HANA

  • New implementation

    greenfield

    A new system with processes redesigned on SAP Best Practices. Usually only master data, open items and balances move.

    Best when processes need a redesign, the ECC is heavily customized or you come from a non-SAP system. The only road to the public cloud.

    Watch the longest average, 20.2 months, and the most change for users. History stays in the old system or an archive.

  • System conversion

    brownfield

    Converts the existing system, with its configuration, custom code and history, using the Software Update Manager.

    Best when the processes still fit and history must stay online. Chosen by 47% in ASUG’s 2026 research, averaging 15.8 months.

    Watch old customizing and custom code travel too. Clean up before converting, and plan the improvements after.

  • Selective data transition

    bluefield

    A reshaped new system loaded with chosen data from the old one, by company code, year or object, usually with specialist tools.

    Best when you want to keep some history and redesign some processes, or merge and split systems along the way.

    Watch dependence on tools and partners, and more complex reconciliation and testing.

Upgrades

Upgrades and implementing the delta

Once you are live, the roadmap carries on in Run: every release has a fixed maintenance window, so upgrades become part of the plan rather than a surprise.

The delta, in two meanings

In an implementation

The delta is what fit-to-standard did not cover: the delta requirements in the Explore backlog, designed and built in Realize. Only the gaps get a design document.

In an upgrade

The delta is only what changed between your release and the target: the simplification items that hit your system, the custom code to adapt, and the new features you choose to adopt.

Technical upgrade: the new release with as little business change as possible. Functional upgrade: the technical upgrade plus new features and processes, which takes longer because it carries scope.

An SAP S/4HANA upgrade, step by step

  1. 1SAP Readiness Check for upgrades: relevant simplification items, add-ons, custom code
  2. 2Maintenance Planner: the target stack and add-on compatibility
  3. 3Sandbox run: a first run on a copy to learn the runtime and the issues
  4. 4Software Update Manager: development, quality, then production
  5. 5Modification adjustment: SPDD for the dictionary, SPAU for repository objects
  6. 6Custom code: ABAP Test Cockpit with the SAP S/4HANA checks
  7. 7SAP Fiori and interfaces: apps, catalogs and integrations checked
  8. 8Regression test and cutover: automated where possible, in a planned downtime window
  • 14 of 687

    simplification items were relevant in a Readiness Check for an SAP S/4HANA upgrade published by a New York State agency in 2025; 7 more needed a manual check.

  • 11 weeks

    for one upgrade case shown at an ASUG chapter event, with four upgrade cycles: sandbox, development, quality and production.

  • 7 years

    is the longest a RISE with SAP private edition customer can go without an upgrade and stay in mainstream maintenance. SAP accepts one upgrade request a year.

  • EHP 6+

    is what an SAP ERP 6.0 system needs for extended maintenance to 2030. The 2033 option also requires moving to SAP ERP, private edition, by the end of 2030.

Starting point

Where you start from changes the project

A company new to SAP, one running ECC for twenty years and one already on SAP S/4HANA face very different problems. Pick your starting point.

Starting point

Coming from a non-SAP legacy

Everything is new: the system, the data model and often the way of working.

The hard parts

  • Data in a different shapeLegacy records must be mapped, cleansed and de-duplicated into SAP objects; customers and suppliers become business partners.
  • How much historyUsually master data, open items and balances move. The rest stays readable in an archive or the old system.
  • No SAP know-how in the houseKey users learn SAP while they design it, and dependence on the integrator is high at first.
  • Processes built around the old systemHome-grown systems often mirror habits nobody questions, until fit-to-standard does.
  • Systems that stayEvery surviving legacy system needs an interface, and someone who still knows it.

Do this

  • Start data cleansing in Prepare, not in Realize
  • Choose key users early and train them before Explore
  • Run at least two mock data loads with reconciliation
  • Agree which reports must match the old numbers at go-live

Coming from SAP ECC

You know SAP, which helps, and you carry years of decisions, which does not.

The hard parts

  • Custom codeYears of custom programs and modifications. Usage analysis often shows a large share unused, and the ABAP Test Cockpit flags what breaks in SAP S/4HANA.
  • Changes that are not optionalBusiness Partner with customer–vendor integration, the material ledger, new asset accounting, SAP Credit Management and the Universal Journal.
  • Finance must reconcile firstGeneral ledger, controlling, assets and stock must agree before the finance data migration, or the conversion stops.
  • Downtime and sizeLarge databases need archiving first and a tested downtime window for the conversion weekend.
  • We already know SAPThe risk is converting old processes unchanged and missing what SAP S/4HANA does better.

Do this

  • Run the Readiness Check early, then again before converting
  • Archive and clean master data before the conversion
  • Choose between conversion, new implementation and selective data transition on facts, not habit
  • Budget extended maintenance as a bridge if go-live falls after 2027

Already on SAP S/4HANA

The move is done. Now the roadmap is about staying current and staying clean.

The hard parts

  • A seven-year clockEach release leaves mainstream maintenance after seven years, five for releases before 2023: upgrades are planned, not optional.
  • Extensions that slow upgradesLevel C and D extensions need checking at every upgrade; level A and B ones rarely do.
  • Regression testingEvery upgrade and feature pack needs a test cycle, and manual testing turns each one into a project.
  • Adopting the deltaNew features arrive every six months. Someone has to decide which ones the business takes.

Do this

  • Keep a release calendar tied to maintenance end dates
  • Automate the regression test set
  • Track clean core levels and retire level D code
  • Review the What’s New Viewer at every feature pack

Quiz

Myth or fact?

Seven things people say about SAP roadmaps and deadlines. Decide, then see the answer.

  1. SAP Activate is a purely agile method.

    Right.Not quite. Myth. Sprints run inside Realize, but phases, quality gates and the go/no-go remain sequential: a hybrid.

  2. On 1 January 2028, SAP ECC systems stop working.

    Right.Not quite. Myth. Mainstream maintenance ends on 31 December 2027. The software keeps running; extended maintenance to 2030 costs two percentage points more.

  3. The 2031–2033 option extends ECC maintenance.

    Right.Not quite. Myth. SAP says it is not a prolongation of maintenance: it is a private cloud subscription for customers who move to SAP ERP, private edition, by the end of 2030.

  4. New implementations take longer than conversions on average.

    Right.Not quite. Fact. 20.2 months against 15.8 in ASUG’s 2026 research, though single projects range from months to years.

  5. Fit-to-standard means no custom development at all.

    Right.Not quite. Myth. Real gaps go into the delta backlog and are built, preferably as clean core level A or B extensions.

  6. Scope items are found in the SAP Best Practices Explorer.

    Right.Not quite. Myth. The Explorer closed on 30 June 2023. Scope items now live in SAP Signavio Process Navigator.

  7. Change management is mostly end-user training.

    Right.Not quite. Myth. Training is one part. Sponsorship, impact analysis, communication and adoption measures make the 7× difference Prosci found.

Pick Fact or Myth on each card.Your score: right out of answered, 7 statements in all.

Frequently asked questions

What is the SAP implementation roadmap?

The plan SAP publishes for running an SAP project: its phases, deliverables, tasks, accelerators and quality checks. Today these are the SAP Activate roadmaps in the Roadmap Viewer, with one roadmap per product and situation, such as a new implementation, a system conversion, an upgrade or RISE with SAP.

What are the phases of SAP Activate?

Six: Discover, Prepare, Explore, Realize, Deploy and Run. Prepare to Deploy are the four core delivery phases, with quality gates between them; Discover comes before the project and Run after go-live.

What were the phases of ASAP?

Five: Project Preparation, Business Blueprint, Realization, Final Preparation, and Go-Live and Support, each ending with a quality check. The Business Blueprint was the signed description of how the company would run its business in SAP.

What is the difference between ASAP and SAP Activate?

ASAP designed on paper first and built in one pass; Activate starts from SAP Best Practices on a working system, validates it in fit-to-standard workshops and builds only the gaps in sprints. ASAP served on-premise projects; Activate covers cloud, on-premise and hybrid.

What is a quality gate in SAP Activate?

A formal checkpoint at a phase transition, where the key deliverables of the phase are reviewed and signed off before the next phase starts. The RISE with SAP Methodology adds clean core checks to a gate at the end of every phase.

How long does an SAP S/4HANA implementation take?

About 15 to 20 months on average. ASUG’s 2026 research found 15.8 months for system conversions and 20.2 for new implementations, with an overall average of about 1.4 years, and its 2024 survey found projects from four months to six years.

How much does an SAP S/4HANA implementation cost?

There is no list price. UK market ranges for 2026 run from about £200,000 in the first year for a small single-entity company to tens of millions of pounds for large enterprises, with software, integrator, data, testing and change management as the main lines.

Greenfield or brownfield?

Greenfield, a new implementation, suits companies that want to redesign processes or come from a non-SAP system. Brownfield, a system conversion, suits companies whose processes still fit and who want to keep history. Selective data transition sits between them.

When does SAP ECC support end?

Mainstream maintenance for SAP ERP 6.0 ends on 31 December 2027. Extended maintenance runs from 2028 to 2030 for an extra two percentage points. After that, the SAP ERP, private edition, transition option covers 2031 to 2033 for customers who move to that private cloud edition by the end of 2030.

References

Checked in October 2026. Costs are indicative market ranges: SAP publishes no price list.